Frequently Asked Questions
The Deutsche Bank Building at 130 Liberty Street
Q: Will LMDC update the Draft Deconstruction Phase 1 Plan to incorporate the results of the Supplemental testing of the interstitial spaces? Will LMDC resubmit the updated plan to the regulators for approval? Top
^
A: Yes. LMDC will update the Draft Deconstruction Phase 1 Plan to incorporate the results of the Supplemental Testing. This updated plan will be submitted to the regulators for approval prior to starting work. LMDC will also incorporate into the revised plan comments received from the Regulators on the 12/10 plan and comments received from the public.
Q: When will the deconstruction start? Top ^
A: The deconstruction will begin after regulatory approval has been given and all necessary permits have been issued to the LMDC.
Q: What regulatory agencies is the LMDC waiting to hear from? Top ^
A: The LMDC has submitted the plan to key regulatory agencies including the U.S. Environmental Protection Agency, The U.S. Department of Labor/ Occupational Health and Safety Administration, the New York State Department of Labor, the New York State Department of Environmental Conservation, the New York City Department of Environmental Protection, the New York City Department of Buildings as well as the city and state Departments of Health and others.